How Long Does Land Clearing Take?
Right after price, this is the question we get most. Somebody is trying to line up a builder, a survey, or a draw, and they need to know when the lot will be ready to hand off. Fair question.
Here is the honest answer, and it is not the one anybody wants to hear. Nobody can tell you without standing on your property. If a contractor gives you a firm number over the phone, sight unseen, he is guessing. Usually he is guessing on the short side, because short numbers win phone calls. The real schedule shows up later and by then it is your problem.
Two lots the same size on the same street can be completely different jobs. What we can tell you is what the clock actually turns on. Know these things about your parcel and you know most of what an estimator knows before he ever walks it.
1. What is actually standing on it
Scattered pines and a season of briar is one machine and a clean sweep. Thick pine over palmetto and scrub oak, with a few mature live oaks mixed in, is a different animal. Density beats size almost every time. Half a lot of heavy timber is more work than a whole lot of light brush.
Big trees are each their own little project. Drop it, buck it, deal with the top, then deal with what is left in the ground. A stand of skinny planted pine you can run through in one pass. A yard full of grandfather oaks in Milton or an old homestead ring of pecans and camphor near Pace, you take those one at a time and you take them carefully, especially if there is anything standing nearby you would hate to hit.
Palmetto is the sleeper. It looks like nothing from the road and it is a mat of root underneath.
2. Whether the stumps come out
Cutting is the quick part. Everything after cutting is where the hours go.
Getting root balls out of the ground and putting the holes back together takes real time, and it is the difference between a lot that looks cleared and a lot that is actually buildable. Once the trees are gone somebody still has to deal with the spoil pile, the holes, and getting the dirt back to grade in lifts that will hold compaction instead of settling under a slab later.
Grinding is faster than digging. Leaving select stumps, on a pasture clear or a driveway cut where nothing is going on top of them, is faster still. Which of those three you are doing depends on what you are building, and that decision moves the schedule more than most of what happens after it.
3. Where the debris goes
This one surprises people. Forestry mulching is the fastest path there is, because the material gets ground up and stays right there. No trucks, no gate, no cycle time, no disposal. If you can live with a mulch mat on the ground, you can be done a lot sooner.
The second you decide everything gets hauled off, the pace stops being about machines and starts being about trucks. A dump truck holds a lot less brush than people picture, brush hauls light and bulky, and the whole job runs at the speed of loads going out and coming back. Where the material has to go matters as much as how much of it there is. Crossing the bay in traffic on every load is its own tax.
That is one place we have an edge. We run our own dirt pit in Navarre at 3125 River Rd, so on a lot of our jobs the material has somewhere close to go and the dirt coming back has somewhere close to come from.
4. How the ground is sitting when we get there
The panhandle helps you in some places and fights you in others.
Out on the sandy ridges from Navarre over toward Destin and Fort Walton Beach, you are in sugar sand. It digs easy, stumps pull clean, and after a rain the water is gone almost before the sky clears, so a crew gets back on it quick. The catch is the low pockets scattered through that same ground where the water table sits close to the surface and it stays soft no matter how sandy it looks. Anything close to the bays and bayous, or down along the Gulf Breeze side, you plan for that.
Move inland toward Crestview, DeFuniak Springs, Freeport and up through the Yellow River basin and it changes. More clay in the subsoil, hardpan in spots, and ground that holds water long after the coast has dried out. The same work takes longer up there and it is harder on equipment.
Then there is our summer storm season, which is its own factor. An afternoon thunderstorm here does not just cost you the afternoon. It can leave the ground too soft to run heavy equipment well after the rain quits, and a tropical system can shut a site down entirely. Work scoped in the drier stretch of the year has a much better shot at running straight through than the same work in the middle of storm season. That is not a promise, it is just what we live with.
Open ground does not stay put around here either. Silt fence and getting something growing back on the dirt are part of the job, not an afterthought. We keep a state certified erosion control inspector on staff, which is one less thing that turns into a holdup at the end.
5. How tight the access is
A wide open parcel with a hard road frontage and room to turn a truck around is the best case. A lot squeezed between two finished houses in Gulf Breeze, with one narrow way in, a soft shoulder, a mailbox, low limbs over the entrance and a neighbor's fence you cannot touch, is a slow lot no matter how little is growing on it.
Tight access changes the machine, and a smaller machine moves less per pass. It also changes how you stage material, whether you can load a truck without blocking the street, and how much of the day gets spent shuffling instead of working.
6. What paperwork is still open
Clearing usually sits behind some kind of approval, and what that looks like depends on your parcel, your county, and what you are trying to build. We are not going to tell you what yours needs, because every parcel is different and the county is the one who tells you. Call them with your parcel number before you move dirt, or call us and we will help you figure out who to ask. We deal with these offices every week and we can walk you through what a lot like yours usually runs into.
Wet ground can bring state and federal agencies into the conversation as well. That part depends entirely on the parcel, so do not take anyone's word for it, including ours. Get it confirmed before you plan around it.
We also get the underground locates called in before we dig, and that is not something that happens the morning of. It goes on the calendar with everything else, which is one more reason a real start date beats a rough one.
One more thing worth saying out loud. If there is an old structure on the property that has to come down first, that is its own piece of work with its own front end, and it generally happens before a clearing crew can do much. We have handled plenty of those and we can line it up.
So what do you tell your builder?
Tell him you are getting a real look at the lot instead of a phone number. Then get somebody out there.
If you want yours on the short end of whatever your lot turns out to need, the moves are simple. Start the paperwork before you start shopping crews, because that is usually the piece that sets your start date. Decide up front whether the debris gets mulched on site or hauled off, and whether the stumps come out or stay. Give us a real start date so we can get the locates called in around it. And if you have any say over when it happens, the drier stretch of the year makes everything easier.